| captureLocation | Porto Tolle |
|---|---|
| storage location | Adriatic Sea |
| facilityTypes |
|---|
| Power generation |
| facilityFeedstock |
|---|
| Coal with biomass firing capability |
| facility size | 660 MWe |
|---|---|
| Total CO2 emissions (without CCS) | 2.50 MtCO2/year |
| plantOperationForRetrofit | 2015 |
| projectTypes |
|---|
| Integrated CCS project |
| captureTechnologyTypes |
|---|
| Post Combustion |
| cO2CapturedFromFacilityFlueGas |
|---|
| 90.0% |
| transport volume |
|---|
| 1.00 MtCO2/year |
| transport distance |
|---|
| 100 km |
| storage type |
|---|
| Saline aquifer |
| storage volume (tonnes) |
|---|
| 10.0 MtCO2 |
| actualVolumeOfCo2Stored |
|---|
| 0.0 MtCO2 |
| projectPartners | ||
|---|---|---|
| Enel | http://www.enel.com/en-GB/ | |
| suppliers |
|---|
| Termokimik |
| Saipem S.p.a. |
| Saipem Energy Service S.p.a. |
| INGV (Istituto Nazionale di Geofisica e Vulcanologia) |
| OGS (Istituto Nazionale di Oceanografia e di Geofisica Sperimentale) |
| ENEA - Ricerca sul Sistema Elettrico S.p.a. (ERSE) |
| IFP (Institute Français du Pétrole) |
| R&D partnerships |
|---|
| Eni S.p.a. (co-operatioon agreement aimed at developing an integrated pilot CCS project and a feasibility study for the construction of a large-scale integrated demo plant at the Porto Tolle power plant); IFP (MoU to test the first generation post-combustion capture process developed by IFP, on the capture pilot plant in Brindisi). |
| projectPhase |
|---|
| testDefine ( more info ) |
| projectOperationalBy |
|---|
| 1 January 2015 |
| project summary |
|---|
| Enel is committed to building a CCS demonstration facility at Porto Tolle, which will capture CO2 present in the flue stream from a power plant, then compressing, transporting and storing it in a saline aquifer. The project involves retrofitting a 660MW coal-fired power-generation group equipped with a post-combustion CO2 capture system at the Porto Tolle plant. The post-combustion capture equipment will be designed to treat a flue gas flow rate of 0.8 MNm3/h, corresponding to a quota equal to the 250 MWe electrical output. The post-combustion capture unit will separate about 1 Mt/y of CO2, which will be transported to an off-shore saline aquifer and injected underground. |
| project policy |
|---|
| ETS, SET plan |
| project permitting |
|---|
| The transposition of the European directive 2009/31/CE related to CO2 storage is ongoing in Italy. |
| project funding sources |
|---|
| EEPR, Corporate |